Izin Mendirikan Bangunan

IMB in Indonesia and Bali: what changed when the PBG replaced it

The IMB was Indonesia's building permit for decades. Since 2021 new buildings get a PBG instead. Here is what an old IMB still does for your villa, and when you need the new documents.

Older Balinese villa with a tiled roof being renovated, a case where the old IMB is replaced by a new PBG

IMB stands for Izin Mendirikan Bangunan, in English a building construction permit. For decades it was the document every Indonesian building needed before it went up. Since 2021, under the Job Creation law and the Public Works ministry's implementing rules, the IMB is no longer issued: new buildings, renovations and changes of use get a PBG (Persetujuan Bangunan Gedung) instead, and a finished building in use gets an SLF (Sertifikat Laik Fungsi). An IMB that was already issued remains recognised for the building it covers.

Cost: an existing IMB costs nothing to keep. A new PBG carries the regency's retribution, and the SLF certificate is free by regulation. See PBG and SLF cost.

IMB vs PBG at a glance

IMB (old) PBG (current) SLF
What it is Permit to build Approval of the technical plans Certificate that the finished building is fit for use
When Before building Before building or changing After construction
How filed On paper at the local office Online through SIMBG Online through SIMBG, then inspection
Status No longer issued Required for new work Required before use

The shift matters in practice. Under the IMB, a permit was granted and the file often closed. Under the PBG, the plans are approved and the SLF later checks the building against them, so a villa built differently from its drawings is caught at the SLF stage.

What an old IMB still covers

If your Bali villa or house received an IMB, keep the original. It shows the building was approved as drawn. You can live in it and keep using it as before. The IMB does not cover:

  • A renovation or extension. An extra floor, a new pool pavilion or more bedrooms need a PBG, with the IMB attached as the previous approval.
  • A change of function. A family house turned into a rental villa, a café or a guesthouse needs a PBG for the new use.
  • Rental or business use. A villa that earns income needs an SLF, and many older IMB villas never received one.

Buying or leasing a villa with an IMB

Compare the IMB drawings with the building in front of you. Bali villas are often extended over the years: a closed-in terrace, a second floor, a staff room. Anything outside the IMB is unpermitted, and you inherit the problem. Our villa due diligence does this comparison before you pay.

Searching for "IMB Bali"

People still say IMB in Bali, and so do some officials. When someone asks for "the IMB" today, they usually mean the building approval, so the current answer is a PBG. If you are planning a project now, go straight to the PBG page and the documents you need.

Good to know

Questions people ask

What is IMB in English?

IMB stands for Izin Mendirikan Bangunan, which translates as building construction permit. It was the permit that allowed a building to be put up, before the PBG replaced it.

Is IMB still valid in Indonesia?

An IMB issued before the change is still recognised for the building it covers. No new IMBs are issued. Any new building, renovation or change of function goes through the PBG.

What is the difference between IMB and PBG?

The IMB was a permit to build, processed on paper at the local office. The PBG is an approval of the technical plans, filed online through SIMBG, and it is followed by an SLF once the building is finished.

My villa in Bali has an IMB. Do I need a PBG?

Not for the building as approved. You need a PBG if you renovate, extend or change its function. If you rent it out, sell it or license it as a business, you also need an SLF.

Can I convert an IMB into a PBG?

There is no automatic conversion. The IMB stays as the record of the original approval. When a change is planned, the new plans are approved as a PBG, using the IMB as the starting document.

What if the building has no IMB at all?

Then it has no approval on record. The plans of the existing building are drawn up and approved first, and the SLF follows. Check this before you buy or lease such a villa.

Talk to the permit team

Have an old IMB?

Send a photo of the IMB and tell us what you plan for the building. We tell you whether you need a PBG, an SLF or nothing at all.

WhatsApp